Case study

Romania's first solar + storage hybrid project

Project details

  • Gorj county solar park
  • 20.4 MW Solar + 2.5 MW Battery Storage
  • Status: Operational (Grid-connected July 2024)

Challenge:

Deliver one of Romania's first utility-scale solar + storage hybrid project within investor timeline, navigating emerging BESS integration requirements and coordinating complex grid connection procedures.

Execution:

Enexus managed the complete project lifecycle under integrated EPC delivery:

  • Permitting and grid connection applications
  • Engineering and procurement of solar + BESS components
  • Construction and commissioning
  • Grid connection and technical acceptance

Outcome:

Project delivered within contracted timeline, achieving grid connection in July 2024. The hybrid installation demonstrated technical feasibility of integrated solar + storage in Romania and established execution precedent for future BESS-integrated projects.

Performance data:

Annual generation 24.5-28 GWh (actual vs projected)
System availability >98% since commissioning
BESS utilization Grid balancing services + arbitrage revenue optimization

Technical performance meets projected generation targets, validating the integrated engineering and procurement approach for hybrid solar+storage installations in Romania's grid environment.